Project Description
The currrent district office and training facility located on Airport Road, is at the end of life cycle requiring increased maintenance costs.Project Location
25490 Airport Rd, Punta Gorda, FL 33950Project Impacts
Additional work was conducted with the building pad fill material due to high moisture content. All testing is completed and passed inspection.Latest Updates
Design: Schenkel & Shultz. Construction Manager @ Risk: Wharton Smith. Construction of the electrical, plumbing, fire sprinkler, ductwork, sound panels, insulation, painting, exterior doors, exterior painting, and finishes is ongoing. Wharton Smith is working with FPL to provide permanent power. We had a Admin. walkthrough on 2/4/2025, which went well, project is on schedule. Florida Power and Light has provided permanent power to the new Charlotte County Sheriff's District 4 Office and Training building. Contractor has poured all concrete sidewalk, irrigation piping has been installed, lift station and HVAC wiring have been completed.
Budget
Phase | Cost |
---|---|
Design | $1,000,000 |
Construction | $8,300,000 |
Total Budget | $9,300,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/11/2021 | 08/15/2022 | 03/17/2022 |
Design Development | 08/15/2022 | 04/13/2023 | 04/14/2023 |
Construction | 10/04/2023 | 06/17/2025 | |
Turnover & Closeout | 06/17/2025 | 07/17/2025 |

Project Phase
Construction
Last Updated
03/12/2025
Project Manager
Pedro Agosto
Public Relations
Brian Gleason
Email Public Relations
Project Number
c892102
Sponsor Department
CCSO
Design Engineer/Architect
Schenkel and Shultz Inc.
Construction Contractor
Wharton-Smith Inc.